On Isle of Palms This November, the Long Walk Moves to the Waterway Side

For most of this year, the island's construction schedule has been about the ocean. The dredge pipe, the fenced work sections and the overnight backup alarms worked their way down the north end of the beach. This month the schedule turns south toward Front Beach and Breach Inlet. On the other side of the island, the elevated Waterway Boulevard path gets its official opening.

The beach work ends on the south end. The Waterway path is complete. And the City's next big job, already in bidding, is at the marina where that path ends. Seen together, these projects explain the next few months on the island. Through the winter, the island's construction is heading from the oceanfront toward the Intracoastal side, and the path built to hold back the waterway is what connects them.

The Sand Reaches the South End

The 2026 offshore renourishment covers up to 2.5 million cubic yards along 19,200 feet of beach. About 800,000 of those cubic yards go on the southern end. That southern stretch is Reach 3, and the City pays for it differently than the rest of the project. On the north end, Reaches 1 and 2 are split 47% City and 53% Wild Dunes Community Association. The City is covering all of Reach 3. The City has received $1.5 million of the $5.3 million it requested in state funding, and that money goes toward the Reach 3 cost.

Weather has already moved the schedule once. On Oct. 19, the City reported that contractor Marinex was over 93% done with Reach 2 and expected about four more days of pumping before moving south. Two days later, rough offshore conditions expected through Oct. 25 kept the dredge from starting back up. The City's tentative schedule calls for Reach 3 pumping to start Nov. 1, run about 45 days and wrap up with demobilization on Dec. 15.

The City's online construction forecast map breaks the south end into segments of about a week each. Here is how that forecast lays out the season. Treat every date as tentative and dependent on weather.

Forecast window for a Reach 3 segment Approximate length
Oct. 30 to Nov. 4 6 days
Nov. 11 to Nov. 19 9 days
Nov. 19 to Nov. 23 5 days
Nov. 23 to Nov. 28 6 days
Nov. 28 to Dec. 4 7 days
Dec. 4 to Dec. 10 7 days
Dec. 10 to Dec. 16 7 days
Nov. 4 to Dec. 11, one longer segment about 5 weeks

The forecast layer and the City's written schedule differ by a day or two at each end. The written schedule says Nov. 1 to Dec. 15, and the map says Oct. 30 to Dec. 16. The City's beach restoration page links to the map and posts updates when the dredge is down.

Those segments show what a south-end morning will look like. The beach stays open. Crews work in fenced sections of roughly 300 yards, and walkers can usually go around them. The exception is temporary dune work, when access past a work zone may be briefly restricted. Sand ramps let people cross the pipeline to reach the water. The heavy equipment runs around the clock, so nighttime lights and backup alarms come with it. The City expects the work to advance 100 to 300 feet a day, so any one stretch should hear it for only a night or two.

The North End Gets Its Dunes Back

While the pipe moves south, the north end goes into recovery. The City's Oct. 16 update said Earth Balance planned to start planting dunes in Reaches 1 and 2 on Oct. 26. Planting both reaches was expected to take about six days, with sand fencing to follow once materials arrived. That timeline assumed Reach 2 would wrap up the week the weather stalled the dredge, so the fencing may come a little later than first planned.

The City has also asked coastal engineering firm Foth for a formal proposal on a possible terminal groin near Breach Inlet. The proposal would cover engineering, permitting and cost. Foth is also set to begin defining the scope of a shoal management project for the north end. The renourishment is the current project, and the City is already studying what could come after it at both ends of the island.

A Path Built to Hold Back the Waterway

While the ocean side is under construction, the City has opened a new route on the Intracoastal side. Phase 2 of the Waterway Boulevard project is complete. The ribbon cutting is Thursday, Nov. 19, at 10 a.m. at the corner of Waterway Boulevard and Forest Trail.

The path also does a second job. The City designed it as a flood barrier, using the December 2023 nor'easter as the benchmark storm. In a storm like that, the raised path is meant to keep Intracoastal water from flooding the homes behind it. The sidewalk has been widened to 8 feet in most places, and check valves now keep tidal water from backing up through the drains. Phase 1 was less visible. It added berms on the golf course that blend into the grass and help protect both the path and the surrounding neighborhood.

On foot, the City's construction updates describe the corridor as running from 21st Avenue to 41st Avenue. A 2022 study by engineering firm Thomas & Hutton measured the path at 1.7 miles. Some gaps remain. A Phase 3 will close two breaks in the barrier near 3607 to 3615 Waterway Boulevard and Fire Station No. 2, and the City is still weighing alternatives there. The project ran several weeks behind this summer because of conflicts with AT&T utilities and the coordination with SCDOT.

Under the forecast map, one Reach 3 segment is set to wrap up on Nov. 19, the same morning the City cuts the ribbon on the waterway side. For the rest of the month, a south-end resident who wants a long, uninterrupted walk has a new 8-foot option on the other side of Palm Boulevard.

Where the Path Ends, the Next Project Begins

The path's north end at 41st Avenue is the island's next construction site. Islander 71 Fish House and Raw Bar, which lists its address as 80 41st Avenue, sits at that end of the route. A 2026 profile in Isle of Palms magazine names Dave and Chrissy Lorenz as its owners.

The marina parking work is on the move. On Oct. 13, the City's Ways and Means Committee unanimously approved a motion on the parking bid after staff recommended Whitestone Construction. The full contract was on City Council's Oct. 27 agenda. City Administrator Douglas Kerr's memo recommends a $472,193 award. That includes a $55,930 change order to move the dumpster enclosure and build a 700-foot bike path, 6 feet wide, from the Waterway Boulevard path to the public dock. The project has $650,000 available, made up of $500,000 from the City and a $150,000 state allocation. The Whitestone contract plus a $5,313 Dominion Energy pole relocation came to $477,506, before a separate electrician's cost that was not yet known.

Construction is scheduled for January and February 2027. The City's Oct. 23 project update notes that the marina restaurant asked for an earlier start, and staff planned to raise that with the contractor. In September, Mayor Phillip Pounds reported that the restaurant lease had been amended to make room for a public-dock greenspace.

The marina has more projects coming after the parking work.

  • Dredging: Permits are in hand, but as of Oct. 23 the City was still waiting on the Army Corps of Engineers to approve placing the dredged material beneath the Isle of Palms Connector. Bids are expected to go to Council in January 2027, and construction can't start until that approval comes through.
  • Bulkhead recoating: Geosyntec is preparing the specifications, and the work is scheduled for winter 2026 to 2027.

After the beach crews leave in mid-December, the marina is next in line, and the bike path to the public dock will connect it to the route opening this month.

The November Calendar, Read Against the Work Zones

The island's calendar runs through these same weeks, and a few dates fall close to the construction milestones.

  1. Thursday, Nov. 5, 5 to 7 p.m.: City Town Hall in the Magnolia Room at the Isle of Palms Recreation Center. It falls during the City's tentative window for south-end pumping and a little over a week after Council's Oct. 27 meeting on the marina contract.
  2. Thursday, Nov. 12, 7:30 a.m.: Sea Stroll & Learn, with whales as the topic. The City's adult programs page says the beach walks meet at the 25th Avenue Beach Access unless otherwise noted. That access is on the south end, so check the forecast map that morning.
  3. Saturday, Nov. 14, 9 to 11 a.m.: Coffee & Canines at the Bark Park behind the Recreation Center. It's free, with acoustic music by Daniel Patrick and coffee from the Rec Center.
  4. Thursday, Nov. 19, 10 a.m.: Ribbon cutting for the Waterway Boulevard path at Forest Trail.
  5. Saturday, Dec. 5, 2 to 7 p.m.: The Holiday Street Festival at Front Beach brings vendors, children's activities, live entertainment and Santa, with the tree lighting at 5:30 p.m. The tentative Reach 3 schedule still has about 10 days left at that point.

The Recreation Center is at 24 28th Avenue, near the middle of the island. Its pickleball courts at 27th Avenue and Hartnett Boulevard host intermediate group lessons Mondays and Wednesdays from Nov. 30 through Dec. 9, 7 to 8:30 p.m.

When a walk ends near Front Beach, The Windjammer's own calendar shows it booking shows this fall. On J.C. Long Boulevard, Acme Lowcountry Kitchen at No. 31 lists breakfast, brunch and dinner daily. A 2026 story in Isle of Palms magazine names Charles Arena as Acme's executive chef and owner. The same magazine also profiles Bret and Kristina Jones of The Dinghy.

If you own a home on the south end and want to know how a wider beach, a raised waterway path and an upgraded marina might change its value, Weichert, Realtors® - Lifestyle is happy to talk it through with you before the dredge leaves in December. Start with Get My Home Valuation, and we'll follow up with a local read on your street.